Accessible Schedule

The project schedule begins in 2021 and continues through 2023. The phases of the project schedule are as follows: Program and concept design - January 2021 to March 2021; schematic design - April to July 2021; final design - August to December 2021; construction - summer 2022 through 2023.

Public and community involvement will occur throughout the project phases. During the program and concept phase and throughout schematic design, the following will occur: stakeholder meetings every two to four weeks; public meetings in February and March 2021; city council briefings monthly from March to July; community briefings on a monthly basis or as requested; senior outreach on a monthly basis or as requested. During the final design phase and as construction begins, some community involvement will continue but may be scaled back once the building design and budget have been approved by the City Council.